24-hour Service Hotline : 0533-8678777 Company Address : No. 5, nanzhi first road, science and technology industrial park, zibo city Purchasing Department: 15805338006(AN) E-mail:sdphkj@163.com Home Page:www.zahiadehar.cn
Peng hui electronic traffic lights manufacturer about lamp installation instructions which steps
Led traffic light installation instructions:
A, install the order details:
1, single lamp assembly;
2, light pole placement;
3, led traffic lights control cable threading;
4, light pole rod connected to the bar and fixed together;
5, assembled, to install the timer, its connection;
6, light direction correction, fixed;
7, Ed traffic signal lamp pole fixed, fastening;
8, signal light pole lifting.
Second, the connection details:
1, each lamp holder by 4 core (that is, three line one standby), from the traffic signal control tractor to stud hand hole of cable some is determined by the number of lamp pole configuration, namely 1 lamp holder used 1 5 core cables, 2 lamp holder using 1 10 core cables, three lamp holder using 1 14 core cables, 4 lamp holder used 2 10 core cables;
Part 2, underground, cable by the traffic signal through embedded tube well to stud hand hole; Part on the ground, each lamp holder to elicit a 5 core cable to stud hand hole, through the stud hand hole and brought the cable connect signal;
3, traffic countdown timer through traffic signal lamp holder wiring, cable quantity negligible;
4, power supply and traffic signal by 3 core section 6 was cable.